TITLE X
PUBLIC HEALTH

CHAPTER 125-O
MULTIPLE POLLUTANT REDUCTION PROGRAM

Mercury Emissions

Section 125-O:18

    125-O:18 Cost Recovery. – If the owner is a regulated utility, the owner shall be allowed to recover all prudent costs of complying with the requirements of this subdivision in a manner approved by the public utilities commission. During ownership and operation by the regulated utility, such costs shall be recovered via the utility's default service charge. In the event of divestiture of affected sources by the regulated utility, such divestiture and recovery of costs shall be governed by the provisions of RSA 369:B:3-a.

Source. 2006, 105:1, eff. June 8, 2006.