TITLE XLI
LIENS

CHAPTER 447
LIENS FOR LABOR AND MATERIALS

Section 447:12-b

    447:12-b Additional Responsibilities; Construction Mortgages. –
I. Within 10 business days of the execution of a construction mortgage, including any refinancing thereof, the mortgagor or his agent shall post in a conspicuous place on the jobsite for which the construction funds were secured, the name, address and telephone number of the institution providing the construction funds.
II. Any person entitled to a lien pursuant to RSA 447:2-7 shall, within 15 business days of the posting required in paragraph I or of commencing to furnish services, materials, supplies or other things, whichever is later, provide written notice to the institution providing the construction funds that such person is furnishing services, materials, supplies or other things. The written notice provided under this paragraph shall include the name and address of the jobsite. Failure to provide the notice required by this paragraph shall not alone invalidate the lien created by RSA 447:2-7.
III. [Repealed.]
IV. In the event that a written contract between the mortgagor or his agent and any person furnishing services, materials, supplies or other things shall provide that the disbursement of construction funds, a portion of which is intended to pay such person, shall be by a 2-party check, the mortgagor or his agent shall transmit a copy of such agreement to the mortgagee. Upon receipt of a copy of such written agreement, the mortgagee shall subsequently disburse funds intended in part to pay any such person only by a check made payable to the mortgagor or his agent and such person. Unless otherwise agreed by the mortgagor and mortgagee, disbursements shall be made only for actual work completed and materials consumed on the jobsite for which the construction funds were secured.

Source. 1991, 270:3, eff. Jan. 1, 1992. 2019, 57:1, eff. Aug. 4, 2019.