TITLE XII
PUBLIC SAFETY AND WELFARE

CHAPTER 162-H
ENERGY FACILITY EVALUATION, SITING, CONSTRUCTION AND OPERATION

Section 162-H:14

    162-H:14 Temporary Suspension of Deliberations. –
I. If the site evaluation committee, at any time while an application for a certificate is before it, deems it to be in the public interest, it may temporarily suspend its deliberations and time frame established under RSA 162-H:7.
II. [Repealed.]

Source. 1991, 295:1. 2009, 65:16, 24, VIII, eff. Aug. 8, 2009. 2014, 217:19, eff. July 1, 2014.